The expected traffic impacts in the Kentucky Transportation Cabinet District 3 area for September 20 through September 27 are listed below. All work is subject to change.

Interstate 165

  • A project to resurface and rehabilitate Interstate 165 in Butler County continues. Crews are milling and resurfacing the roadway in both directions from mile point 26.4 to mile point 32.8. Motorists should expect lane closures in this area. The speed limit will be lowered to 55 mph. Motorists should use caution as crews will be working close to the roadway. The project is expected to be completed by November 1.

Barren County

  • U.S. 68 (mile point 0.0 to 10.0) – Crews will continue drainage work in the area.

Butler County

  • KY-70 (mile point 8-11).  Mobile operations and one-lane traffic at times to complete edge line rumbles and striping.

Logan County

  • KY 3240 (mile point 0.0 to 2.1) – A resurfacing project is expected to continue in this section of KY 3220. The project is between Russellville High School and U.S. 68. The work is being done at night from 6 p.m. to 6 a.m. Motorists should expect lane closures and delays.

Warren County

  • Commonwealth Boulevard – A repair project for the bridge on KY 3145 over Commonwealth Boulevard in the Kentucky Trans-Park in Warren County continues. Commonwealth Boulevard is closed near KY 3145 and is scheduled to reopen on Nov. 15. The schedule is subject to change. A signed detour using Prosperity Road, Production Avenue, Fred Madison Road, Jody Richards Drive and U.S. 68 is in place.